Kit Assembly Consultant |
![]() |
![]() |
Consultant, an independent Sub-contractor
To view over 1,000 pictures of the Ai dome under construction....from land excavation, to foundation construction, to dome kit assembly, to interior finishing, please click on Ai dome construction. If you do not have the time or do not want to assemble the dome shell kit, American Ingenuity can refer you to a Assembly Consultant operating out of Florida. He will travel to your construction site providing "Hands On" work while supervising your workers or subs or your contractor's workers to get your dome shell assembled with the first layer of concrete in the seams and a "scratch coat" on the entryways and dormers. Then either you complete the interior finishing or your contractor hires local conventional subs (plumbers, electricians, drywall finishers, framers, etc.) to complete the interior finishing and the installation of your locally purchased doors and windows. Prior to the availability of this Kit Assembly Consultant to work and supervise the dome kit assembly, Ai's clients had to hire a contractor who generally had never assembled a dome before. As a result the contractor would tend to over charge because he did not know how long it would take or what problems would arise. The Kit Assembly Consultant can provide you with references from previous American Ingenuity Domes he has assembled so you can assure yourself that your building kit will be assembled correctly and in a timely fashion. This Consultant would work directly for you or your general contractor as an Independent Sub-Contractor. The standard rate for the Kit Assembly Consultant is $265 per day plus travel from his Florida home to your job site and a return to his home at the completion of the job. If you supply a place for him to stay, shower facilities, TV and food, his rate is $200 a day plus travel to your site and back to Melbourne Florida. The use of a consultant for one week can save you up to two weeks of shell assembly time. For Dome Construction sites in Florida, the Consultant can drive a Boom Truck to your site for use in assembly for a cost of $225 a day for the days it is in actual use on the site, plus mileage costs to your site and back to Rockledge Florida and sales tax. The rental of the boom truck saves you money. It carries the lifting spikes, steel hubs and the 135 2x4's that are precut and color coded which get assembled to make the temporary wooden rib system that supports the panels while the seams, entryways and dormers are concreted. Normally each client:
By renting the boom truck, the client does not pay the above $1,800 in items. After the kit is assembled the rib system comes down, and the 2x4's and the steel hubs and lifting spikes that were brought to the job site on the boom truck are returned to Ai via the boom truck. If you are are a Florida client interested in using the Kit Assembly Consultant or the Boom Truck, call Ai's office at 321-639-8777 Monday thru Friday 9-5 eastern time. To unload the dome kit from the semi-truck, you rent a fork lift and have 2-3 workers available. Ai provides a document that describes the unloading process. The Boom Truck could be used:
The dome owner provides three good workers, preferably one of whom has some masonry or stucco experience. Materials used in the shell construction are to be provided by the owner on site before the Kit Assembly process begins. The bags of cement don't have to all be delivered in advance but as soon as first needed during the assembly. To view what items are included in the Dome Building Kit, click on Kit Contents. To view what items are not included in the kit, click on Items Not Included. Due to possible injury on a job site, have some form of insurance. The following are items required at the job site: Cement
Sand
Misc Items:
Additional Items Required without the Boom Truck:
How Long Will Shell Assembly Take?
Using three to four good laborers and depending upon the size dome, soil condition around the dome to allow movement and placement of the panels, hoisting mechanism you use and prevailing weather, shell assembly can take from 7-16 days if your dome kit includes two entryways, four dormers and no cupola. Once you know how many entryways and dormers are needed for your floor plan, our office can give you a more specific estimate on shell assembly time. Click on Hoisting Mechanisms to learn more. Typically it is cost effective to only have the Consultant stay until the kit and building options are assembled which includes the first coat of concrete in the seams and a "scratch coat" on the entryways and dormers. Then your workers can:
As far as finishing the seams, no need to pay the consultant by the day for this. Best to hire a local finish stucco person by the hour with the conditions if he does timely work and good work, you will retain him. If you are not satisfied with his work or speed, pay him for the time worked and replace him. Once your Building Plans have been ordered, American Ingenuity can estimate the number of days needed to assemble the shell. Each floor plan varies as to the number of building kit options (components) needed to complete the shell kit; i.e. cupola, link, entryways, door dormers and window dormers. Building Options take longer to install than triangles do. To learn more about Building Options, click on Options. You or your contractor hires local subcontractors to perform the typical jobs like forming and pouring the slab, plumbing, electrical, framing, drywall finishing, etc. We don't believe you should pay someone to come in from out of county or state to do work that your local subs can perform. Click on Finished Cost, to learn about what it will cost to finish your dome home. Click on Builders and Assemblers to learn more. A helpful web site is rsmeans.com It has construction manuals, construction estimating CD's, etc. Another helpful web site that sells construction cost estimating programs is www.ezhomebuild.com About 40% of American Ingenuity's clients assemble their own dome shell kit themselves, many with no construction experience. The prefabricated panels come marked with numbers and letters to match the Assembly Manual that comes with the Dome Building Kit. The dome building plans also have elevation views with numbers and letters. The Assembly Manual must be read, inventory sheet kept posted and the building plans followed to assure success. If some questions come up, don't hesitate to call us.
Of course, the labor costs to assemble the dome shell kit are much less when you assemble the kit yourself with the help of family members or friends.
If you are employing a contractor to assemble the kit, an experienced consultant on the construction site will make the assembly go faster and reduce costs. The contractor provides the additional workers needed and the consultant directs them through the assembly of the kit. The consultant does not stand around...he is a working consultant.
If you choose to hire the Kit Assembly Consultant, the following labor estimates assume the following:
The cost of materials to complete the assembly of the kit are not included in the labor estimates.
The assembly time estimated below is based on a dome kit having two entryways, four dormers and no cupola.
ESTIMATES FOR PLANNING PURPOSES ONLYThe following assembly times are estimated averages for general planning purposes only! The times will be affected by inclement weather, worker productivity, site accessibility, changes in wage rates, rental rates, etc. Estimates are include the following: All Panels placed with first layer of concrete in the seams and a "scratch" coat on the entryways and dormers. Includes two standard entryways and four dormers and the assembly and disassembly of the temporary wooden rib system. Finish stucco on seams, entryways and dormers is not included. Entryways and dormers are not framed in and windows and doors are not installed. Labor Estimates & Equipment for dome shell assembly
using a Consultant
|